If you’re planning a build, it helps to know when your builder needs to be paid and when your lender can release the funds. Construction loans often pay out in stages. We’ll walk through what that means for your budget, paperwork and build schedule.
Why the money is released in stages
The lender considers the land and the proposed completed property as part of the security. Releasing funds gradually, against evidence that work has been completed, is how the lender manages that risk. It also means you generally pay interest only on what has been drawn, rather than on the full amount from day one.
The stages you can expect
The following is an illustration, not a payment schedule. Stage names, amounts, deposit arrangements and evidence requirements vary by lender and contract.
- Deposit and land. Where land is part of the purchase, that portion is usually funded first.
- Base or slab. Once the foundation is poured and inspected.
- Frame. Once the frame is up and inspected.
- Lock-up. Once the roof, windows and external doors are in place.
- Fixing or fit-out. Once internal work such as cabinetry, tiling and wet areas is complete.
- Practical completion. Once the build is finished and the final payment is released.
Before each release, the lender usually wants evidence the stage is complete. That is commonly a progress inspection, a valuation or a signed builder’s claim, depending on the lender and the contract.
What the lender looks at before it approves the loan
In addition to financial evidence, the lender may ask for project-specific information such as:
- A fixed-price building contract with a licensed builder, plus the builder’s registration and insurance certificates.
- Council approvals such as building permits and, where relevant, planning approval.
- Plans and specifications that match the contract.
- A cost breakdown showing the amount allocated to each stage.
- The land position, including whether it is owned, being purchased, or already encumbered.
- Your contingency. Cost overruns are common, and the arrangements for covering them should be understood before work starts.
What can delay a progress payment
- Timing between stages. A stage cannot normally be paid before it is complete, so if the builder expects payment earlier than the contract allows, that gap has to be managed.
- Variations. Changes to the build after the contract is signed can fall outside the approved amount, and lenders treat them differently depending on paperwork and size.
- Valuations. A lender may assess the proposed completed value and request progress inspections. An inspection for lending purposes is not a substitute for independent building-quality advice.
- Delays. Weather, trades and approvals all move timelines. Interest-only periods and contract dates are worth discussing in advance rather than during a delay.
- Insurance. Builder’s warranty and construction insurance requirements differ by state and territory, and they are worth confirming rather than assuming.
How to keep the build on track
- Match the contract’s stage payments to the lender’s release schedule before signing anything.
- Keep a written record of every variation, signed and dated.
- Confirm who is responsible for inspections at each stage, and allow time for them.
- Hold a genuine contingency rather than relying on the loan to stretch.
- Keep the lender informed of delays early. Ask what a delay means for the loan terms and funding schedule; additional time or funds are not automatically approved.
Where a renovation differs
A renovation can be funded in more than one way. A smaller project might be covered by a standard loan with access to funds, or by equity released against the existing property. A structural renovation that changes the home substantially can look more like a construction loan, with staged payments and inspections. The right structure tends to depend on the size, the contract and the lender’s view of the finished value.
Common questions
How long does a construction loan run for?
Some facilities use interest-only repayments during construction and change to principal and interest afterwards. The repayment basis, allowed construction period and extension process depend on the contract. Confirm what happens if completion is delayed.
What if the build runs over budget?
Compare the revised cost with the approved finance and available savings before agreeing to a variation. A signed variation does not automatically increase the loan. The lender may require reassessment, and you may need to cover the difference yourself.
Should you buy the land first?
The sequence affects funding, holding costs and contractual commitments. Compare the options with your lender and legal adviser, including what happens if the build is delayed. A land purchase does not guarantee later construction finance.
Explore your options
Keep exploring

Property investing
Using equity to buy your next property
How usable equity is worked out, how it can fund a deposit, and the risks worth understanding before you commit.
This is general information, not a recommendation for your circumstances. Loan availability, features, costs and approval depend on the lender and your situation. Seek qualified legal, tax or financial advice where needed.